Kell Roadway Improvements Complete by Spring

Find out the status of Northeast Cobb road construction projects.

The following are updates about Northeast Cobb road construction from Cobb County Department of Transportation:

Jamerson Road and Wigley Road

Kell High School roadway improvements consist of various improvements for the Jamerson and Wigley roads. Jamerson Road has been widened from a two lanes to a four lanes divided road from Lee Waters Road to Canton Road. Jamerson and Wigley roads have been widened from two lanes to three lanes from Sandy Plains Road to Lee Waters Road.

Find out what's happening in Northeast Cobbwith free, real-time updates from Patch.

The four-lane roadway will transition to a three-lane roadway with right turn lanes at intersections. Kell improvements include extension of turn lanes along Lee Waters Road. This project also includes the construction of six retaining walls.

The project is currently under construction with expected completion Spring 2012.

Find out what's happening in Northeast Cobbwith free, real-time updates from Patch.

Canton Road Corridor

Construction complete.

County Line Road

Safety improvements and better traffic flow for the County Line Road corridor are near completion. Bad weather and utility delays prolonged the project, according to the Cobb DOT.

The project consists of approximately five miles of roadway improvements on County Line Road between Due West and Mars Hill roads. Improvements include reconstruction of five intersections, replacement of the bridge over Allatoona Creek, replacement of the culvert north of Burnt Hickory Road, and widening of the existing two-lane roadway. The curb, gutter and sidewalks have been added. A roundabout has been installed at the intersection of County Line and Burnt Hickory roads.

The project completion date is the end of March.

Noonday Creek Trail

Work continues on the nearly seven mile long Noonday Creek Trail, which will connect pedestrians and cyclists from the Town Center mall area to Kennesaw Mountain National Battlefield Park.

In Northeast Cobb, the trail is still under construction. It runs northward along Barrett Lakes Blvd. to Noonday Creek. From Noonday Creek, the trail runs under I-75, crosses Busbee Parkway at Town Center Drive, goes under I-575 and Chastain Meadows Parkway before ending at the western side of Bells Ferry Road. A small gravel parking lot on county owned land just off of Bells Ferry Road will be a trailhead.

This phase of the project is expected to be complete by summer.

Sandy Plains at East Piedmont Road- GDOT

Construction continues to widen the roadways to provide additional left turn and right turn lanes at each intersection approach. The intersection improvements include dual left turn and right turn lanes on all four quadrants of the intersection, median modifications, curb and gutter, sidewalks, crosswalks and ADA ramps. The existing traffic signal has been upgraded.Β 

The project should be complete May 2012.